Install the billboard between the two monitors. At this time, be sure to connect the left hand side connector.
Remove the shipping bracket, and install the bank guards on
the left and right sides.
Connect 2 connectors on each bike.
By adjusting the height of the front cabinet's leg levelers, insert
the bike mechanism.
Secure with 6 hexagon bolts per side.
Install floor side left and right and floor center as shown below.
At this time, adjust the leg levelers to ensure that the floor
is level with the ground.
The machine has 11 casters and 10 leg levelers. When the game
has been moved to its final installation location, adjust all
the leg levelers upward and ensure that the casters are at least
5 mm above the floor, and that the machine is level.