4 . ASSEMBLING AND INSTALLATION

 

Assembling should be performed as per this manual.Since this is a complex machine, erroneous assembling may causedamage to the machine, or malfunctioning to occur.

When assembling, be sure to perform work by plural persons.

Depending on the assembly work, there are some cases inwhich performing the work by a single person can cause personalinjury or parts damage.

When installing the billboard, it is difficult to carryout work by one person. To perform work properly and safely, besure work is performed by at least two people.


Note that the tools such as a phillips screwdriver and wrenchfor M16 hexagon bolt w/24 mm width across flats are required forthe assembly work.

When carrying out the assembly work, follow the procedure inthe following 6-item sequence:

 

1. ASSY OF PTV

 

2. WIRING CONNECTIONS BETWEEN CABINETS

 

3. SECURING IN PLACE (ADJUSTER ADJUSTMENT)

 

4. POWER SUPPLY

 

5. TURNING POWER ON

 

6. ASSEMBLING CHECK

 

To perform work safely and securely, be sure to prepare a stepwhich is in a secure and stable condition. Not using a step orusing an unstable step can cause a violent falling down accident.